EDUCATION AND OUTREACH
Wetland Education Center

|
The first stage of the
Wetland Education Center (WEC)
will create a 2.5 acre salt marsh on-site at UTMSI. Material
excavated from the site will be used to create 1.5 acres of
sheltering dunes around the site. Creating the WEC is a joint
project between the USACE and The University of Texas under
Section 206 of the Waterways Restoration Act.
The Marsh will have two separate
tidal access points and be planted with high & low salt marsh
plants: smooth cordgrass (Spartina alternaflora)
and black mangrove (Avicennia germinans); submerged
seagrasses. |
The second stage will include the
construction of public boardwalks, an amphitheater, educational
signage and floating educational program platforms. A K-12
curriculum has been developed for the WEC.
In progress photos
WEC Timeline
-
Construction of the wetland was
completed on May 4, 2007.
-
The shoreline must stabilize for 60
days prior to plantings.
-
Marsh planting will begin in early to
mid-summer.
-
Boardwalk construction will begin in
late summer.
Topographic Habitat Creation Map
|